Tuesday 30 April 2013

Day 62 - Tile roof complete

Saturday 27th April extra safety platforms went up around the house
Monday 29th colour bond rear roof and all gutters installed
Tuesday 30th all roof tiles on, and heating and cooling ducts started to be installed