Sunday, 23 June 2013

Day 116 - Upstairs Hebel Rendering completed

One day blue board

 
the next its rendered with the Hebel.
 Progress is has been good, Hebel is all done and the rendering will be done sporadically until complete, starting at the balcony and working forward and down as other construction completes




Friday, 14 June 2013

Day 107 - Second Floor Hebel Progressing and nearly fully laid

The weather has been less than perfect, and the Hebel team have pushed on, and have almost fully laid the external walls.

It has been 8 months since I first visited a Carter Grange display, and only 4 months since our construction started.  We are a little behind my estimated progress plan, but nothing that can't be recovered.

No worthwhile pics to share, just a muddy site with scaffolds obscuring the external walls.

The chippy has been planing joists and installing ground floor doors, and the  pre-wiring seems complete.

Hopefully some nice progress and pics this week

Friday, 7 June 2013

Day 100 - Ready for top floor hebel

This week has seen a little work on the ducts, foil wrap completion on the top floor, some data cable laid and scaffold construction. Fresh hebel and blueboard has been delivered, just waiting for a crew to show up and install.  :-)
I have just been informed by both site managers that RH liked the job so much that he will replace DL for the rest of the build. They are both great, so it works for me. 

Monday, 20 May 2013

Day 82 - Scaffold has come down, now the insulation and hebal can go up, and the roofing can be finalised

No other action though.
Promised solar panels not installed, and unlikely to be now due to the scaffolds being down - until the wall scaffolds reach the roof again). 
The rain may be keeping everyone away - from my place, and two other CG builds in the area that I can see (2 builds within 500 metres of our temp accommodation)