Saturday, 27 July 2013
Day 150 - skirting boards in upstairs
Plaster false walls added under stairs
and extra bulkheads above cabinets.
Floors leveled and skirting installed.
Latches being added to doors
And balcony ready for tiles
Tuesday, 23 July 2013
Day 146- Roof looking complete, stairs complete, balcony ready for tiles, as are the benches
Sunday, 23 June 2013
Day 116 - Upstairs Hebel Rendering completed
One day blue board
the next its rendered with the Hebel.
Progress is has been good, Hebel is all done and the rendering will be done sporadically until complete, starting at the balcony and working forward and down as other construction completes
Thursday, 31 January 2013
Day (27) - Plans complete
Plans approved for new house - just need to demolish the old house