Tuesday, 23 July 2013
Wednesday, 26 June 2013
Day 119 - Ready to tile garage roof
Roof trusses have been built, tiles delivered, scaffold erected - only thing missing is someone to place the tiles on the roof - hopefully tomorrow.
Quad has been nailed to the eaves, and work has commenced on connecting the downpipes to the roof. Lockup must be close
Quad has been nailed to the eaves, and work has commenced on connecting the downpipes to the roof. Lockup must be close
Monday, 20 May 2013
Day 82 - Scaffold has come down, now the insulation and hebal can go up, and the roofing can be finalised
No other action though.
Promised solar panels not installed, and unlikely to be now due to the scaffolds being down - until the wall scaffolds reach the roof again). 

The rain may be keeping everyone away - from my place, and two other CG builds in the area that I can see (2 builds within 500 metres of our temp accommodation)
Tuesday, 30 April 2013
Day 62 - Tile roof complete
Saturday 27th April extra safety platforms went up around the house
Monday 29th colour bond rear roof and all gutters installed
Tuesday 30th all roof tiles on, and heating and cooling ducts started to be installed
Monday 29th colour bond rear roof and all gutters installed
Tuesday 30th all roof tiles on, and heating and cooling ducts started to be installed
Wednesday, 17 April 2013
Day 49 - Roof trusses arrive and go up
We now have the skeleton of a house, balcony is almost complete, steel frames seem complete, rear trusses are up, main house trusses are up and as of last night we are only missing the trusses over the master bedroom and the garage.
Drive by in the morning on the way to work of the trusses being delivered, most of which were installed by the time I had a look in on my way home from work (below)
This is a view of the flat roof trusses from the dining room, and the balcony trusses behind over the kitchen
Getting dark early, but this is the roof trusses over the rear balcony.
Drive by in the morning on the way to work of the trusses being delivered, most of which were installed by the time I had a look in on my way home from work (below)
This is a view of the flat roof trusses from the dining room, and the balcony trusses behind over the kitchen
Getting dark early, but this is the roof trusses over the rear balcony.