Work has started today on the underpinning - close to 3 weeks lost due to this issue alone
After and before shots of the under pinning
Perhaps it is too early for me to appreciate the value of this work, it has been noticed that the fence is now missing some support, and the neighbours are complaining about the road being ripped up by visiting machinery, not to mention my disappearing driveway
Showing posts with label Neighbours. Show all posts
Showing posts with label Neighbours. Show all posts
Monday, 18 March 2013
Friday, 8 March 2013
Day 9 - Meeting our Construction Project Manager and our construction phase Administrator
Met with DL, as he explained what was involved in the underpinning to the neighbours. I have seen his work personally in a house he constructed around the corner and as detailed in Hyatt38's blog. He strikes me a competent professional and I look forward to working with him (or his working on my house at any rate).
EW has been assigned as my construction administrator, and she seems like another competent and dedicated individual, if she looks after us half as well as BB did in the contract stage I will be very happy indeed.
Bad news is that we won't have a slab until the end of the month, but on the flip side the good news is that we should have a slab poured by the end of the month, and perhaps the frame erected. I am useless at this waiting game, but that is how the cards are at the moment. No work can start until the underpinning is completed, and the underpinning could not be scheduled until the neighbours have agreed to it, and it takes time.
EW has been assigned as my construction administrator, and she seems like another competent and dedicated individual, if she looks after us half as well as BB did in the contract stage I will be very happy indeed.
Bad news is that we won't have a slab until the end of the month, but on the flip side the good news is that we should have a slab poured by the end of the month, and perhaps the frame erected. I am useless at this waiting game, but that is how the cards are at the moment. No work can start until the underpinning is completed, and the underpinning could not be scheduled until the neighbours have agreed to it, and it takes time.
Day 9 - underpinning
Our new house required a good deal of earth works where we basically excavated so that we could have some level building platforms to construct out home on, this has meant that our drive way is lower than the neighbours and there is a possibility, though very remote that their carport could collapse before we have the retaining wall in place, so for a mere few thousand dollars I will pay to extend their foundations more deeply than they are, and thus ensure their asset is protected. In order to do this I need to get their consent, and they need to understand the implications this has for them before providing that consent. This has taken over 1 week, but is now in place and further work can be scheduled to get my site started.
My advice is if underpinning is mentioned as a possibility, then get the consent straight away as the only risk is that the engineers may decide it is unnecessary but you will have no real delay. My delays started with the half week to even be able to inform the neighbours of the need, then the week and a half to get the consent and be able to act on it.